NOTE: Dates assigned to items are to be considered just indicative.
Items marked with refer to new developments.
Items marked with will involve contribution from external sources interested in the project.
Items marked with will require coordination with more than one Working Group.
- Solids and volumes:
- Tunable tolerance
by April 30th, 2007 - New specific extruded-solid shape
by April 30th, 2007 - New specific paraboloid shape
by September 30th, 2007
- Tunable tolerance
- Navigation & optimisation:
- Parallel navigator, completed migration
by June 30th, 2007 - Optimised navigation for voxelised phantom geometries
by July 31st, 2007 - Integration of Geant4e, error-propagation module
by October 31st, 2007
- Parallel navigator, completed migration
- Robustness checking & performance tuning:
- Full application tuning (benchmark suite) with field
by April 31st, 2007 - Field performance tuning/benchmark
by May 31st, 2007 - Review response precision of solids on points close to surface and normals. Verify accuracy of 2nd order equations
by May 31st, 2007
- Full application tuning (benchmark suite) with field
- General code review and improvements:
- Refactoring and revision of biasing/scoring processes
by June 30th, 2007 - Review of navigator implementation for double calls and behavior on coincident surfaces
by September 30th, 2007 - Review of field user classes
by September 30th, 2007 - Code review for BREP specific solids
by October 31st, 2007 - Review implementation of Boolean solids
by November 15th, 2007
- Refactoring and revision of biasing/scoring processes
- Routine activities
- Extend testing suite for solids (CSG/specific/Boolean/BREPS)
- Review of user documentation and publication of a paper on a refereed journal