Work items for 2007

 
Version 1.1

 

NOTE: Dates assigned to items are to be considered just indicative.
Items marked with refer to new developments.
Items marked with will involve contribution from external sources interested in the project.
Items marked with will require coordination with more than one Working Group.

  1. Solids and volumes:
    • Tunable tolerance
      by April 30th, 2007
    • New specific extruded-solid shape
      by April 30th, 2007
    • New specific paraboloid shape
      by September 30th, 2007
  2. Navigation & optimisation:
    • Parallel navigator, completed migration
      by June 30th, 2007
    • Optimised navigation for voxelised phantom geometries
      by July 31st, 2007
    • Integration of Geant4e, error-propagation module
      by October 31st, 2007
  3. Robustness checking & performance tuning:
    • Full application tuning (benchmark suite) with field
      by April 31st, 2007
    • Field performance tuning/benchmark
      by May 31st, 2007
    • Review response precision of solids on points close to surface and normals. Verify accuracy of 2nd order equations
      by May 31st, 2007
  4. General code review and improvements:
    • Refactoring and revision of biasing/scoring processes
      by June 30th, 2007
    • Review of navigator implementation for double calls and behavior on coincident surfaces
      by September 30th, 2007
    • Review of field user classes
      by September 30th, 2007
    • Code review for BREP specific solids
      by October 31st, 2007
    • Review implementation of Boolean solids
      by November 15th, 2007
  • Routine activities
    • Extend testing suite for solids (CSG/specific/Boolean/BREPS)
    • Review of user documentation and publication of a paper on a refereed journal

 

Major items above prioritized and with description

 