Work Plan for 2013
Version 1.1
- Continue in applying coding guidelines:
- Review the status and update the table on the Wiki page
(1)
- Progress with the examples not yet completed
(1,2)
- Review the status and update the table on the Wiki page
- Migration to MT
- Identify the examples which should be migrated
(1,2)
- Migration of selected examples with help of MT team
(2)
- Identify the examples which should be migrated
- Migration to g4tools
(1,2)
- Continue in the code review:
- Apply the reviewer recommendations in the examples already reviewed (electromagnetic, Hadr01, Hadr02)
(1,2)
- Call for new reviewers (in the whole collaboration)
(1)
- Proceed with new reviews
(1,2)
- Apply the reviewer recommendations in the examples already reviewed (electromagnetic, Hadr01, Hadr02)
- Complete removal of novice examples (N01, N02, N03)
(1)
(1) First semester
(2) Second semester
Items marked with
refer to WG core developers.
refer to WG members, example owners
refer to all volunteering G4 members
Previous years planned activities
2012 2011 Created: 04 February 2013
Last modified: 22 February 2013, by Ivana Hrivnacova